Recently, Wuxi ZOZEN Boiler Co., Ltd. helped an LNG company to quickly complete the transition from the old to the new of the thermal oil heaters for the 300000 nm³ LNG liquefaction production line, saving the economic losses of the enterprise and ensuring the normal supply of liquefied natural gas in local area.
Commissioning of ZOZEN Gas-fired Thermal Oil Heater on site
With the continuous advancement of environmental protection, the demand for natural gas has surged all over the world. In order to alleviate the shortage of natural gas, the customer company decided to invest in the construction of a LNG liquefaction production line in local area with a daily processing capacity of 300,000 Nm³.
However, only six years after the project was put into operation, the original thermal oil heater was burned out and could not be used normally, which let the customer company in a difficult situation for a time. At this time, in a short period of 20 days, ZOZEN Boiler helped the customer company to complete the supply and commissioning of the new thermal oil heater, which lowered the loss of the customer company.
Full View of ZOZEN Boiler Plant
On Mar. 19th, ZOZEN Boiler received a message for help through the official website, the sales manager learnt that a set of 2 million kcal thermal oil heater was in urgent need. There were finished products meeting the requirements in ZOZEN's warehouse. On the next day, the customer company and ZOZEN Boiler confirmed the details of cooperation and signed a purchase contract.
On Mar. 22nd, ZOZEN Boiler gave priority to the delivery of the boiler through multi-party coordination. Three days later, the boiler successfully arrived at the project site. ZOZEN thermal oil heater is factory packaged, after it is in place at the construction site, it only needs to install burners and build the furnace, and it can be debugged and run by turning on gas and electricity.
One-step forming for round coil of ZOZEN thermal oil heater
In order to quickly put the boiler into operation, the after-sales engineer of ZOZEN Boiler rushed to the installation site on holidays, helped the customer accept the installation quality of the boiler and debug the burner. According to the on-site feedback, the burner was successfully ignited, and it took a certain time for the thermal oil to be transported to the site. It was expected to complete the commissioning of the boiler on April 7.
In the face of such rapid boiler service, the head of the customer company said: "the speed of ZOZEN Boiler is beyond everyone's expectation, we are very satisfied. In addition, judging from the details of the boiler's construction, the boiler's refractory mortar is built very carefully, and the appearance is more beautiful than that of the previous one."